Norochcholai Generator Shut Down for Maintenance; Kelanitissa Plant to Resume Operations

The Ceylon Electricity Board (CEB) has announced that Generator No. 1 at the Norochcholai coal power plant will be taken offline from midnight today (13) for scheduled maintenance, which is expected to last around 25 days.

CEB spokesperson Dhammika Wimalaratne stated that the temporary shutdown will reduce the national grid’s capacity by 300 megawatts, posing a significant impact on Sri Lanka’s power generation.

To help offset the shortfall, the Kelanitissa Combined Cycle Power Plant—out of service for the past one and a half months due to maintenance—is set to resume operations from midnight tonight, contributing 165 megawatts to the grid.

Wimalaratne added that the timing of these maintenance works was carefully planned, considering the ongoing rainy weather, which has increased the potential for hydroelectric power generation.

Leave a Reply

Your email address will not be published. Required fields are marked *

You cannot copy content of this page