Audit Reveals Failures in Railway Telecom Project

According to the National Audit Office, the Railway Telecommunications System Upgrade Project is not being implemented effectively.

Although the project, aimed at improving the efficiency of railway services, was completed in November 2020, the expected outcomes have not been achieved.

This finding was revealed through a performance audit conducted by the Audit Office.

Several major shortcomings were identified, including the failure of responsible officials—both individually and collectively—to integrate with the system, the Railway Department’s failure to ensure system maintenance through the contracted communications agency as per the agreement, and the absence of an effective monitoring mechanism for overall system operations.

Although a circular was issued by the Railways Department mandating the use of communication system equipment for official duties, some officers failed to comply.

The Audit Office has recommended disciplinary action against those who violated the circular and neglected their responsibilities.

It also advised the establishment of a comprehensive signal coverage network across the island to ensure the successful and uninterrupted operation of the system